District Projects
Welcome to the North Washington Street Water & Sanitation District's District Projects page. This page provides updates on current and upcoming water and sanitary sewer infrastructure projects throughout the District.
Our goal is to keep customers, residents, businesses, contractors, and developers informed about projects that improve the reliability, safety, and long-term sustainability of the District's water and wastewater systems.
Project Information
- Status: Active Construction – Water Main Installation and Testing Underway
- Contractor: Colorado Civil Infrastructure
- Location: Washington Street from 59th Avenue to 66th Avenue
- Final Completion: February 16, 2027
Washington Street Cast Iron Water Main Replacement Project
Phase 1 – 59th Avenue to 66th Avenue
Construction Update | November 24, 2026
The North Washington Street Water & Sanitation District continues to make significant progress on the Washington Street Cast Iron Water Main Replacement Project. This project replaces aging cast iron water mains to improve system reliability, reduce the potential for water main breaks, and ensure dependable water service for our customers.
Construction Progress
Crews have completed new water main installation through the 62nd Avenue intersection and are currently progressing south toward the Union Pacific Railroad crossing. Water service connections between 64th Avenue and 62nd Avenue have been completed, with final water main connections remaining at the 64th Avenue intersection.
Preparations for the railroad crossing are moving forward, including coordination with railroad representatives and scheduling of preliminary construction activities.
Upcoming Construction Activities
Over the next two weeks, construction activities are anticipated to include:
- Continued water main installation south of 62nd Avenue.
- Completion of remaining water main connections at 64th Avenue.
- Concrete, curb and gutter restoration in previously completed construction areas.
- Asphalt milling, paving and roadway striping, weather permitting.
- Preliminary work associated with the Union Pacific Railroad crossing.
- Continued abandonment of existing cast iron water mains as replacement sections are placed into service.
Traffic and Water Service Impacts
Motorists should continue to anticipate temporary lane restrictions, traffic pattern changes and construction-related delays along Washington Street. Please exercise caution when traveling through the construction zone and follow all posted traffic control signs.
Residents and businesses affected by planned water service interruptions will receive advance notification. The District and its contractor will continue working closely with affected customers to minimize disruptions.
All construction and restoration schedules remain subject to weather conditions, railroad coordination and unforeseen field conditions.
Thank You for Your Patience
The District appreciates the continued patience, understanding and cooperation of residents, businesses and motorists throughout this important infrastructure improvement project.
We remain committed to completing construction safely and efficiently while minimizing impacts to the surrounding community.
North Washington Street Water & Sanitation District
Providing reliable water and sanitation services to our community.
Emergency Water Main Replacement — 75th Place and Washington Street
Following several water main breaks along this section of pipe, District crews are replacing the failed 6-inch cast iron water main extending from Washington Street to 75th Place. The replacement will improve service reliability and reduce the likelihood of future breaks and service disruptions.
Water main replacement and pavement restoration were completed on October 30, 2026.
27-Inch Sewer Main Replacement Near the Metro Lift Station
The District is replacing aging sewer main and manholes near the Metro Lift Station with new 27-inch PVC sewer pipe and Armorock polymer concrete manholes. These improvements will support reliable wastewater service and provide long-term protection against the corrosive conditions found in the sewer system.
Upcoming Water Main Replacement — 58th Avenue and Franklin Street
Construction Update – November 24, 2026
Plans have been finalized for the replacement of the 16-inch water main at 58th Avenue and Franklin Street. A pre-construction meeting was held on November 18, and the pipe and fittings have arrived at the District office. Final preparations are underway, with construction anticipated to begin in December 2026.
District crews will complete the project in-house, utilizing their experience, equipment and resources to improve water system reliability, control construction costs and maximize the value of ratepayer dollars.
Additional updates regarding construction schedules, anticipated traffic restrictions and potential water service interruptions will be provided before work begins.
The District appreciates the continued patience and cooperation of residents and businesses as we work to improve and modernize our water distribution infrastructure.
